The southern grid lost 36.2% of the electricity it bought in July 2026, the distributor's data shows
EDESUR's open data reports 704 GWh of energy bought for its network and 254.9 GWh lost across 6 southern zones in July 2026, leaving 449.1 GWh billed. Losses therefore equalled 36.2% of the energy the distributor put into the network, the measure EDESUR and the energy ministry use. The ministry's twelve-month rolling rate for EDESUR stood at 32.0% to June 2026.
Listen to this reportHouse voice · belowWhat the record shows
- 704 GWh bought, 254.9 GWh lost and 449.1 GWh billed across 6 zones, July 2026
- Losses equalled 36.2% of the energy put into the network, the publisher's own measure
- EDESUR's twelve-month rolling loss rate was 32.0% to June 2026 in the ministry's series
Read the chart as data
| Period / category | Loss |
|---|---|
| Barahona | 60.6 |
| Bani | 50.6 |
| San Cristobal | 47.6 |
| Santo Domingo | 45.8 |
| San Juan | 26.2 |
| Distrito | 15.8 |
What remains unknown
- The split between technical losses and theft, which the dataset does not break out
- The ministry's figure for July 2026, which had not been published when this correction was made
- How the month compares once demand is accounted for
Go to the source
EDESUR energy delivered and lost (open dataset, ODbL)
EDESUR Dominicana · primary
Scope: South Watchlist · Period: 2026-07
Retrieved: 3 Sept 2026, 14:02 AST
THE NULL BRIEF · REPORT READER
Read it. Or press play.
Listen to the report, including its sources and what remains unknown.
Story 1 of 1 · The southern grid lost 36.2% of the electricity it bought in July 2026, the distributor's data shows
View listening queue · 1 stories
Prefer your device’s own voice? Accessibility reader
The Device voice button reads the same text with an installed English voice on your device. It is not a NULLPEN house recording.
Read your selected briefing About 1:54 at a measured reading pace · estimate, not audio duration
STORY 1 · Infrastructure & Mobility · CORRECTION
The southern grid lost 36.2% of the electricity it bought in July 2026, the distributor's data shows
NULLPEN. Synthetic narration. Report published 2026-09-03. Infrastructure & Mobility. South Watchlist. Evidence state: correction. Data period: 2026-07. The southern grid lost 36.2% of the electricity it bought in July 2026, the distributor's data shows. EDESUR's open data reports 704 GWh of energy bought for its network and 254.9 GWh lost across 6 southern zones in July 2026, leaving 449.1 GWh billed. Losses therefore equalled 36.2% of the energy the distributor put into the network, the measure EDESUR and the energy ministry use. The ministry's twelve-month rolling rate for EDESUR stood at 32.0% to June 2026. Correction: Correction, 6 September 2026: an earlier version of this report said the southern grid lost 26.6% of the electricity it handled in July 2026. That figure divided losses by purchased energy plus losses. Under the measure EDESUR and the Ministry of Energy and Mines use, losses as a share of the energy the distributor buys, the rate was 36.2%. The zone chart has been redrawn: Barahona 60.6%, Bani 50.6%, San Cristobal 47.6%, Santo Domingo 45.8%, San Juan 26.2%, Distrito 15.8%. The GWh figures were correct; 'delivered' meant energy bought for the network. What remains unknown: The split between technical losses and theft, which the dataset does not break out. The ministry's figure for July 2026, which had not been published when this correction was made. How the month compares once demand is accounted for. Sources: EDESUR Dominicana. The publication date is not the data period. Read the full record and sources on nullpen.com.
Read the evidence and sourcesNULLPEN Reader 01 and Reader 02 are disclosed synthetic house voices, rendered once per approved script on NULLPEN’s own equipment and served as fixed recordings. Playback is user initiated; a correction withdraws the affected recording. Your narrator and topic choices stay in this browser.
Device voice is synthetic speech using an installed English voice, not NULLPEN Reader 01 or 02. No NULLPEN model API or paid speech-generation call. A topic change stops the previous queue. House recordings, when available, remain separately rights-checked.